Over the summer, these four Capital Improvement Plans (CIP) will be completed.
- Renovation of the Cafeteria and 2nd Floor Student Bathrooms to replace and upgrade the
plumbing and associated fixtures. Of note: the original plan was to renovate all three sets of
the student bathrooms but due to recent significant cost increases for materials and supplies,
we will only be completing two sets of bathrooms this year. The staff will document the
requirements for the renovation of the remaining bathrooms in the building as a separate
CIP project.
- The STEM Room Conversion to renovate the obsolete configuration of the room and to
create more available classroom space. This classroom was originally designed as a computer
lab with concrete block “desk” workstations to support the heavy desktop computers and
CRT display devices. The wiring for power and network connectivity was built into the
concrete block support structure. This was very efficient at the time but is very obsolete now
with the proliferation of portable / hand-held wireless computing equipment. Removing the
three rows of block infrastructure will open up the classroom for more effective, and
flexible, utilization.
- Propane Tank Repairs identified during the 2021 inspection process of the campus 18,000
gallon underground tank that services the entire building will be completed;
- Parking Lot Resealing and Line Striping as part of a regular 5-year maintenance cycle.